Autodesk Fusion Operations allows different approaches to assigning Machines to a Production Order. Continue reading this article to learn about each option. Check this article to learn how to create a Machine.
How to assign a machine to a new Production Order?
There are several ways to assign machines to production orders.
Assigning the Machine manually
Check this article to learn how to create a Production Order.
1. Navigate to the Production Orders menu in the Side panel (1) and click on Add Production Order (2).
2. Open the “Advanced Fields” in the Production Order Screen.
3. Select the machines from the list or search for the specific one and click on it to assign (1). Remember to Save Production Order (2).
Assigning the Machine via import.
Autodesk Fusion Operations also allows you to assign Machines while importing multiple Production Orders.
By adding the Machine codes (separated by commas) in the importer, they will be automatically linked to the respective Production Orders upon import.
Check this article to learn how to import multiple Production Orders (POs).
How to assign a Machine to an existing Production Order?
1. Navigate to the Production Orders menu (1), search for the PO code (2) to which you want to assign the Machine/s. You can click on the code (3) or click on the pencil icon (4) from the action menu to edit the PO.
Check this article to learn how to use the Filters to search for a specific Production Order.
2. In the Production Order screen, scroll down to navigate to the Advanced Fields (1), select the Machine from the dropdown (2), and Save the Production Order (3).
If you still have some doubts, feel free to reach out to us via live chat feature or directly to your CSM.